How to check your installation opening of movable wall
Measure the opening height at both ends and at 2-3m distances in the track line.
Make sure that:
- End walls are plumb. If this is not the case check whose responsibility it is to make them plumb. In the head the possible straightening may be achieved by adjustable aluminum joint profiles. Make sure that the adjustment is big enough. At the telescopic panel end check if some adjustment lath or corresponding is needed on the permanent wall.
- Floor is level and flat enough
- Structure where track is fixed to is durable enough
- There will be nothing (e.g. air ducts or cable ladders) to be installed in the track line or in the storage area that could restrict track installation.
Make sure that storage area:
- Height is at least the same as in that movable wall line
- The track line planned to the storage area is clear. (No projections hindering panel movements beside the permanent wall).
If you have any additional questions about installation opening of movable walls, please contact Movable Wall team using our contact form.